2558
|
Wednesday, April 03, 2024, 10:48 |
chad fisher | South Hot-Cell | Maintenance | | | SE Manipulator wrist swap | On April 2, 2024 the wrist on the SE manipulator
of the SHC (Serial # 7986) was swapped with
a rebuild unit originally from SW position |
|
|
2599
|
Friday, May 24, 2024, 08:10 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#45 | UCx#45 Installation | On Wednesday, May 22, 2024 UCx#45 was installed
on TM4 in the SHC. Installation was normal
other then minor issue with the multipin |
|
|
2681
|
Monday, September 16, 2024, 08:23 |
chad fisher | North Hot-Cell | Repair | | | Model N Remote end #9352 reapir | On Friday, September 6, 2024 Model 'N'
remote arm #9352 was removed from the NHC
right side installed position to investigate |
|
|
2682
|
Monday, September 16, 2024, 08:48 |
chad fisher | Manipulator Maintenance | Maintenance | | | CRL Technicain Manipulator Maitenance Trip | Over the course of September 9th - September
13, 2024 a CRL manipulator technician carried
out the following manipulator maintenance: |
|
|
2743
|
Wednesday, January 08, 2025, 07:37 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#46 | UCx#46 removal | UCx#46 removed from TM4 and placed into
a pail back-filled with argon. Nothing visually
unusual; no issues. |
|
|
1267
|
Tuesday, June 21, 2016, 13:47 |
Travis Cave/ Dan McDonald | Spent Target Vault | Repair | | | Spent Target Vault Door | The spent target vault door does not open
or close. The emergency door closing did
have to be used to close the door as it was |
|
|
5
|
Tuesday, July 19, 2011, 11:17 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#35 | Move of TM#4 from East target station to south hot cell. | Move went well no problems readings at
East Target Station were very high at 500mSv/hr. |
|
|
7
|
Tuesday, July 19, 2011, 12:02 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#36 | Electrical check | See attached PDF for the details. |
|
|
10
|
Wednesday, July 20, 2011, 09:55 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#36 | Move of TM#4 from South Hot Cell to East Target Station. | Move completed, move went well. |
|
|
13
|
Monday, July 25, 2011, 14:49 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#35 | Spent target move | Ta#35, in pail #88, has been place into
spent target storage, in spot 6C. Upon removal
from the South Hot Cell it was 411mSv/hr |
|
|
14
|
Wednesday, July 27, 2011, 14:34 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | | Module move | TM#1 has been moved from the Conditioning
Station to the South Hot Cell for the installation
of Ta#37. |
|
|
15
|
Thursday, July 28, 2011, 12:02 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#37 | Electrical check | TM#1 has passed the the electrical check. |
|
|
16
|
Thursday, July 28, 2011, 14:07 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | Ta#37 | Module move | Tm#1 with Ta#37 moved from the south hot
cell to the conditioning station. Move went
well. |
|
|
18
|
Wednesday, August 03, 2011, 11:24 |
Travis Cave | ITW | Standard Operation | TM1 | Ta#37 | Module move | TM#1 with Ta#37 has been moved from the
conditioning station to the the west target
station, move went well. |
|
|
27
|
Wednesday, September 14, 2011, 10:32 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#37 | Spent target move | Ta#37 has been moved from the south hot
cell into the storage vault. The target is
in pail #89 and in spot 6A in the vault. |
|
|
28
|
Wednesday, September 28, 2011, 09:07 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#36 | Move of TM#4 from East target station to south hot cell. | Move of TM#4 with Ta#36 from East target
station to south hot cell, move went well. |
|
|
30
|
Wednesday, September 28, 2011, 11:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | no target | TM#4 moved from South Hot Cell to to North East Silo. | TM#4 moved from South Hot Cell to to North
East Silo, move went well. |
|
|
31
|
Thursday, September 29, 2011, 11:11 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#36 | Spent target move | The spent Ta#36 has been moved to the storage
vault. It was placed in pail #90, and placed
into slot 3B, it was 111mSv/hr upon removal |
|
|
32
|
Monday, October 03, 2011, 11:00 |
Travis Cave | ITW | Standard Operation | TM1 | UCx#2 | Move from west station to south hot cell | TM#1 with UCx#2 has been moved from the
west station to the south hot cell. Move
went well. |
|
|
34
|
Monday, October 03, 2011, 14:52 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | TaC#1 | Electrical check | TM#1 with TaC#1 installed passed the electrical
test. With a value of 882MOhms that was meggered
from the heat shield to the chassis, all |
|