Message ID: 1864     Entry time: Thursday, January 31, 2019, 14:16
Author: Isaac Earle 
Category: North Hot-Cell 
Type: Development 
Module:  
Target/Number:  
Subject: NHC grounding approval 

 Franco Mammarella was consulted regarding electrical grounding of the NHC design (RS103 of Document-131915).  After discussing the design, and having grounding inspected by Randy Boehm, Franco approved the design and advised that the grounding system should be inspected periodically.  This task has been added to the Remote Handling inspection index on an annual schedule.  A PDF copy of the e-mail correspondence with Franco is attached.

Attachment 1: NHC_grounding.pdf  112 kB  | Show | Show all