Message ID: 186     Entry time: Thursday, September 20, 2012, 09:16
Author: David Wang 
Category: Conditioning Station 
Type: Standard Operation 
Module: TM1 
Target/Number: Nb#7 
Subject: TM1 Nb#7 target heat shield helium pressure check is done. 

Leak detector pumped down to base LR1.3xE-9 atm.cc/sec, and BP 8xE-3 torr. All high vacuum gauge readings at CS and TM1 are at low -6 range from 1.2xE-6torr to 4.6x E-6 torr. Applied 80 psi helium  to heat shield circuit for 5minutes and there is no any response on leak detector. The heat shield circuit is leak tight.