Today;
Restoring shielding at M9 T2 area and cleaning up RH setup.
- RH workbench, pole tray and bridges removed from work site.
- 18' x 6' by 3' bridging block removed (at 14:25) to reveal the T2 monument. No apparent change in vacuum, will monitor as shielding is restored.
- Magnet power tests completed by beamlines group, no issues reported.
- Rubber testing ring installed between M9 Q1 and T2, see photo.
- Spring eye gaps appear to be the same as on Friday (after 48h), see photos and video.
Work continues re covering the M9 T2 site tomorrow. |