Cleaned up work site and removed extraneous poles and tooling. Radioactive parts stored in lead flask now located on TNF.

- Two pins, an RH bullet bolt and indium ring (tb22148) were put into lead flask for storage, flask now located on TNF.

- Took photos of spring eye gaps and some video inspection, looks roughly the same as yesterday (see photos).

- Installed a dust cover over the east spring pin (see photos).

 

Looking at placement of indium rings loaded with EPDM and Buna N at joint for radiation exposure. Will install the test rig on Monday & clean up site for covering up.

Attachment 1: 20121019_RH1_01_0081.JPG  3.747 MB  | Show | Hide all
Attachment 2: 20121019_RH1_01_0082.JPG  3.559 MB  | Hide | Hide all
20121019_RH1_01_0082.JPG
Attachment 3: 20121019_RH2_02_0004.JPG  2.950 MB  | Show | Hide all
ELOG V2.9.2-2455