Entry  Monday, April 15, 2024, 10:52, Aaron Schmidt, Fixed, , Ar Glove box RP swapped. 
 Monday, April 15, 2024, 10:50: The old IDP15 RP was not pumping the antechamber down properly. An exchange IDP15 pump is loaned to us from vacuum
group. Once the tip seals on it are replaced, we will swap it again.
Applicable work permit: I
Entry  Thursday, July 11, 2024, 13:40, Aaron Schmidt, , , Q2 - 2024 Ball Mill Calibration & Inspection  Q2_-2024_Ball_Mill_Calibration_&_inspection.jfifQ2_-_2024_Clean_up.jfif
Fritsch Pulverisette 5 Ball Mill status:
Thursday, July 11, 2024, 13:39:
SN 05.6010 / 03005: Inspected. Ok. Was dirty inside. Cleaned.
Entry  Thursday, November 21, 2024, 11:48, Aaron Schmidt, , , Change glove on Ar Glove box (2) 
 Thursday, November 21, 2024, 11:46: 2 Glovebox gloves were changed. The far right glove & the far left glove. 
No contamination was found on the sealing edges of the glove box. Both old gloves were placed in bags & placed in the alpha waste bin.
Work Permit: 
Entry  Monday, December 16, 2024, 12:15, Aaron Schmidt, Completed, , Q4 - 2024 Ball Mill Calibration & Inspection  Q4_-_2024_Ball_Mill_Calibration&_Inspection.png
 Fritsch Pulverisette 5 Ball Mill status:
Monday, December 16, 2024, 12:12:
SN 05.6010 / 03005: Inspected. Ok. 