Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Lab Maintenance, Page 4 of 4  Not logged in ELOG logo
ID Date Authordown Status Test Subject
  50   Thursday, November 30, 2023, 10:03 Aaron SchmidtFixed Ar Glove box - Blower / solenoid fix

 On November 10th / 11th a site wide power outage occured. Once power was restored, the Ar glove box had intermittent issues with the solenoids & blower. The blower did not start & the solenoids often got stuck or ceased operating. 

Yesterday Randy B inspected the connections to see if they were receiving enough power. It was good from the main plug-in, through to the PLC, however was dead at fuse positions 3 & 4 on the rear panel. Both fuses were changed, but that did not help. We did some fidgeting in the back & the solenoid function returned. It was left overnight.

Thursday, November 30, 2023, 08:30: <- Approx. Initial check: Dropped a crumpled Kimwipe inside the glove box to check for air flow / blower function. It did not move. Blower was not functioning, but the solenoids did. De-energized the glove box completely. 

Removed the old corroded fuse holders, added a pair of modified new ones. Cleaned a couple of corroded critical connections. Installed the new fuses, re-plugged it back in. Function returned to normal. The Kimwipe was also moving, verifying the blower is again operational. 

Thursday, November 30, 2023, 09:51: Complete. 

  51   Tuesday, December 12, 2023, 13:12 Aaron Schmidt  Q4 - 2023 Ball Mill Calibration & Inspection

   Fritsch Pulverisette 5 Ball Mill status:

Tuesday, December 12, 2023, 13:11:

SN 05.6010 / 03005: Inspected. Ok

SN 05.6000 / 00365: Currently disassembled / out of service. (Under Process status until repaired, re-assembled, inspected, & tested)

  54   Friday, February 09, 2024, 11:01 Aaron Schmidt  Laser cutter inspection

 Friday, February 09, 2024, 11:01: Epilog laser cutter operates. OK

  57   Monday, April 15, 2024, 10:52 Aaron SchmidtFixed Ar Glove box RP swapped.

 Monday, April 15, 2024, 10:50: The old IDP15 RP was not pumping the antechamber down properly. An exchange IDP15 pump is loaned to us from vacuum group. Once the tip seals on it are replaced, we will swap it again.

Applicable work permit: I2024-04-12--2. Status: Returned. 

  59   Thursday, July 11, 2024, 13:40 Aaron Schmidt  Q2 - 2024 Ball Mill Calibration & Inspection

Fritsch Pulverisette 5 Ball Mill status:

Thursday, July 11, 2024, 13:39:

SN 05.6010 / 03005: Inspected. Ok. Was dirty inside. Cleaned.

SN 05.6000 / 00365: Currently disassembled / out of service. (Under Process status until repaired, re-assembled, inspected, & tested)

  63   Thursday, November 21, 2024, 11:48 Aaron Schmidt  Change glove on Ar Glove box (2)

 Thursday, November 21, 2024, 11:46: 2 Glovebox gloves were changed. The far right glove & the far left glove. 

No contamination was found on the sealing edges of the glove box. Both old gloves were placed in bags & placed in the alpha waste bin.

Work Permit: I2024-11-21-2

Note* Changing both inner gloves is recommended later. We had considered to do both however the O2 ppm spiked after the change of the first two. We were at 185 ppm & aim to not cross 200 ppm.


Additional info:

The remaining gloves were inspected and appeared in acceptable condition.  A regeneration was performed shortly after and the gas lines, pump lines were also inspected.  This will be considered as the inspection for the current inspection cycle.

Darwin

  64   Monday, December 16, 2024, 12:15 Aaron SchmidtCompleted Q4 - 2024 Ball Mill Calibration & Inspection

 Fritsch Pulverisette 5 Ball Mill status:

Monday, December 16, 2024, 12:12:

SN 05.6010 / 03005: Inspected. Ok. 

SN 05.6000 / 00365: Currently disassembled / out of service. (Under Process status until repaired, re-assembled, inspected, & tested)

 

  65   Friday, February 14, 2025, 14:17 Aaron Schmidt  Laser Cutter Inspection.

Friday, February 14, 2025, 14:16: Epilog laser cutter operates. OK.

Blower, red dot, adjustments settings ok. Laser used to cut Ta foil. OK.

ELOG V2.9.2-2455