27
|
Friday, September 27, 2019, 13:55 |
Aaron Schmidt | | | DI water supply leak outside room 06 - ISAC B1 | Friday, September 27, 2019, 13:54:
There is a pin hole water leak coming
from the DIW supply pipe going into the ISAC |
|
28
|
Wednesday, December 18, 2019, 13:50 |
Aaron Schmidt | | | Q4-2019 Ball Mill calibration & inspection | Fritsch Pulverisette
5 Ball Mill status: |
|
30
|
Wednesday, April 08, 2020, 11:40 |
Anders Mjos | | | Lab check in | Checked in on the labs and other equipment
yesterday. Everything looks ok, including
the glove box Ar supply. Recorded O2 and |
|
31
|
Friday, April 24, 2020, 16:27 |
Anders Mjos | | | Lab check in |
|
|
32
|
Monday, July 13, 2020, 11:07 |
Aaron Schmidt | | | Eye wash temp | Temp was noted to be high @ 50 deg
C.
Adjusted the regulators to 35 deg |
|
33
|
Monday, July 13, 2020, 11:23 |
Aaron Schmidt | | | Q2 - 2020 Ball mill inspection | Fritsch |
|
35
|
Wednesday, September 16, 2020, 10:42 |
Aaron Schmidt | | | Ball Mill troubleshoot. | Odd noises reported. Darwin &
Marla. "Like a rock caught in a
fan" |
|
36
|
Friday, December 04, 2020, 12:58 |
Aaron Schmidt | | | Q4 - 2020 Ball Mill Calibration & Inspection | |
|
37
|
Tuesday, February 09, 2021, 06:56 |
Aaron Schmidt | | | Planned power outage. | Tuesday, February 09, 2021, 06:53: Evaporator
2 off. Evaporator 1 ok, Fume hoods ok. Ar
glove box off. Ready for planned power outage. |
|
38
|
Tuesday, August 03, 2021, 10:34 |
Aaron Schmidt | | | Q2 - 2021 Ball Mill Calibration & Inspection | |
|
39
|
Tuesday, December 07, 2021, 09:23 |
Aaron Schmidt | | | Q4 - 2021 Ball Mill Calibration & Inspection | Tuesday, December 07, 2021, 09:23:
SN 05.6010 / 03005: Inspected. |
|
40
|
Thursday, January 20, 2022, 13:38 |
Carla Babcock | | | Testing of spare FUG bias supply | Tomislav and John Chow tested the spare
bias supply located in the rack of the electrical
services room. This is a FUG HCN 1400 M-60000, |
|
43
|
Tuesday, July 12, 2022, 11:08 |
Aaron Schmidt | | | Q2 - 2022 Ball Mill Calibration & Inspection | Fritsch
Pulverisette 5 Ball Mill status:
|
|
44
|
Friday, December 16, 2022, 07:36 |
Aaron Schmidt | | | Q4 - 2022 Ball Mill Calibration & Inspection | Fritsch Pulverisette
5 Ball Mill status: |
|
45
|
Thursday, February 02, 2023, 10:30 |
Aaron Schmidt | | | Eyewash & Shower Station OK | Thursday, February 02, 2023, 10:14:
Cold Lab Eyewash & shower station ran.
Ok. |
|
48
|
Friday, June 30, 2023, 12:21 |
Aaron Schmidt | | | Q2 - 2023 Ball Mill Calibration & Inspection | Fritsch |
|
49
|
Tuesday, August 01, 2023, 12:31 |
Darwin Ortiz Rosales | | | Evap1 and Evap2 Inspection and Maintenance | Evap1: Cleaned and checked seals.
Oil level could not be clearly determined,
but are consulting with pump group to check. |
|
51
|
Tuesday, December 12, 2023, 13:12 |
Aaron Schmidt | | | Q4 - 2023 Ball Mill Calibration & Inspection | Fritsch |
|
54
|
Friday, February 09, 2024, 11:01 |
Aaron Schmidt | | | Laser cutter inspection | Friday, February 09, 2024, 11:01:
Epilog laser cutter operates. OK |
|
56
|
Wednesday, March 27, 2024, 13:42 |
Keyur Chauhan | | | Actinide Mass Balance Calibration ISAC-I B1 Hot Lab | ISAC-1