Entry  Wednesday, April 26, 2023, 09:48, Darwin Ortiz Rosales, TiC, 44692-5, LP-FEBIAD, Done, TiC230425 
    Reply  Wednesday, April 26, 2023, 18:20, Carla Babcock, TiC, 44692-5, LP-FEBIAD, In progress, TiC230425 
       Reply  Wednesday, April 26, 2023, 22:26, John Wong, TiC, 44692-5, LP-FEBIAD, In progress, TiC230425 Screenshot_2023-04-26_221720.jpg
          Reply  Thursday, April 27, 2023, 06:30, Darwin Ortiz Rosales, TiC, 44692-5, LP-FEBIAD, Done, TiC230425 
             Reply  Thursday, April 27, 2023, 21:48, Carla Babcock, TiC, 44692-5, LP-FEBIAD, In progress, TiC230425 MicrosoftTeams-image_(36).png
             Reply  Thursday, April 27, 2023, 22:18, John Wong, TiC, 44692-5, LP-FEBIAD, In progress, TiC230425 Screenshot_2023-04-27_204948.jpgScreenshot_2023-04-27_205012.jpgScreenshot_2023-04-27_220239.jpgScreenshot_2023-04-27_220323.jpgScreenshot_2023-04-28_010640.jpg
                Reply  Friday, April 28, 2023, 09:39, Darwin Ortiz Rosales, TiC, 44692-5, LP-FEBIAD, Done, TiC230425 MicrosoftTeams-image_(20).png
Message ID: 629     Entry time: Thursday, April 27, 2023, 21:48     In reply to: 628
Author: Carla Babcock 
Target Material: TiC 
Target Oven W.O#: 44692-5 
Source: LP-FEBIAD 
Status: In progress 
Subject: TiC230425 

Darwin Ortiz Rosales wrote:

John Wong wrote:

Carla Babcock wrote:

Darwin Ortiz Rosales wrote:

Wednesday, April 26, 2023, 09:32

LP FEBIAD loaded with 367 TiC discs and 4 TiC removable discs for analyses

50 packs of 5 and the rest are singles

TaC coated (sintered) springs placed at both ends

Initial total Weight = 521.83 g

Initial heating @ 1A/min to 400 A on TGHT and 280A on TBHT

OMEGA slope = 0.99

Vacuum limits up to 200A:  3.0e-05 Torr -- 5.0e-04 Torr

Vacuum limit up after 200A: 3.0e-05 Torr -- 5.5e-05 Torr

No Ta heat-shields used

Initial IGP1 = 4.1e-07 Torr


Wednesday, April 26, 2023, 09:49

Starting initial ramp up to 200A on both TGHT and TBHT @ 1A/min


Wednesday, April 26, 2023, 12:50

Around 120A on TGHT, the pressure started to slowly drop.  First outgassing done.


Wednesday, April 26, 2023, 14:03

IGP1 = 6.0 e-05 Torr

TGHT = 200 A, 2.7V

TBHT = 200 A, 2.6 v

OMEGA = Below lower limit

Waiting for pressure to fall below 5e0-5 Torr.  Will change bad vacuum to 5.0e-05 Torr and then continue ramping @1A/min to 400 A on TGHT and 280 A on TBHT.


Wednesday, April 26, 2023, 14:13

IGPI= 4.2 e-05 Torr

starting ramping to 400 A on TGHT and 280A on TBHT 


Wednesday, April 26, 2023, 14:26

The IGP1 pressure just fell below 3.0e-05 Torr and ramping has resumed


Wednesday, April 26, 2023, 14:42

pressure hovering around good vacuum so very slow progress.


Wednesday, April 26, 2023, 15:12

TGHT= 223 A, 3.1 V

TBHT = 226 A, 3.0 V

Set ramp rate is 1A/min but real rate is slightly less than 0.5A/min due to pressure fluctuation.

 Vacuum spike at 300A.

Currently:

TGHT= 316A, 4.6V

TBHT=283A, 3.9V

Wednesday, April 26, 2023, 18:18 Ramping TBHT down from 280A to 270A

 Wednesday, April 26, 2023, 22:12

TGHT = 400A, 6.1V; TBHT = 274A/3.7V. Temp is holding sturdy ~1100 C and will leave it overnight.

Pressure is coming down, currently at 8.8 e-6 Torr.  See attachment for the overview. 

TGHT will continue to ramp up tomorrow morning; check the pressure to ensure it has come down below 5e-6 Torr before proceeding.  Refer to the instructions for details.   


 

 

 Thursday, April 27, 2023, 06:27

IGP1= 1.7e-06 Torr

OMEGA= 1097 C

TGHT= 400A, 6.2V

TBHT= 273A, 3.7 V

Starting ramp up of TGHT @0.2A/min set to 550A

 Reached 550A on TGHT (paused there until I realized it was stopped) then resumed ramping to 580A at 0.2A/min. Saw both vacuum spikes before 550A. Attaching screenshot from John.