Tuesday, June 07, 2022, 07:19
Total number of foils: 403 ( including 5 analysis discs on the right side of the container)
Total weight = 1535.3 g (includes heatshields, spring and T bar)
Total length packed 16.4 cm (excluding 5 analysis discs that will be removed)
container has 3 Ta heat shields.
No endcaps inserted to facilitate out-gassing
Ta coated spring at front (right) side
Initially to ramp TGHT and TBHT to 50A at 3 A/min
then continue to 80A and slow down ramp when pressure begins to increase
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 3.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 7.6 e-07 Torr at start of initial ramp.
Tuesday, June 07, 2022, 11:14
Ramping to 150A on TGHT and TBHT at 1A/min
Ramped TGHT and TBHT to 230A at 2A/min
Tuesday, June 07, 2022, 13:12
Ramping TGHT to 600A at 4A/min
TBHT at 230A, 3.0V
Tuesday, June 07, 2022, 16:41
TGHT= 740 A, 12.1V
TBHT= 232A, 3.0 V
OMEGA reading 1616C but questionable. Will leave for 4 hours at 740A top TGHT.
Wednesday, June 08, 2022, 22:15
Early Wednesday morning the left TGHT bolt was found damaged. The target leg was coated with bolt material rendering the Target inoperable.
The Heatshield assembly was swapped and surfaces cleaned. A "dummy" FEBIAD was installed to test if the system can withstand high current.
The system was pumped down and ramped to 740A on TGHT at 4A/min. It was then left at that current for 4 to 5 hours.
Currently starting rampdown at -2A/min to 0A.
Photos of the incident attached in *eLog 580*. IGP1= 5.7e-06 Torr
TGHT= 742A, 11.4V |