Tuesday, July 02, 2013, 11:13, Peter Kunz , UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013)
|
Thursday, July 11, 2013, 16:22, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013)
|
Monday, July 15, 2013, 09:45, John Wong, UO2/C, Target boat #2, , Done, Processing UC2 flakes (batch#05 - 18062013)
|
|
Message ID: 70
Entry time: Tuesday, July 02, 2013, 11:13
Reply to this: 71
|
Author: |
Peter Kunz |
Target Material: |
UO2/C |
Target Oven W.O#: |
Target boat #2 |
Source: |
|
Status: |
Done |
Subject: |
Processing UC2 flakes (batch#05 - 18062013) |
|
|
1. stage - burning off organics complete
2. stage - carbonization began 1-8 am 2013/07/02 |
|