Wednesday, July 07, 2021, 14:39
Target Provisional ID = 200929 was installed in the EVAP1 and pumped down (Tuesday July 7, 2021).
Target is going to be thermally reduced for 8 hours and then conditioned for an additional 8 hours
IGP1 = 2.0 e-6 Torr
Good vacuum = 1e-1 Torr
Bad vacuum = 5e-1 Torr
Power desired 1.6kW.
10 extra discs included for analysis
Wednesday, July 07, 2021, 14:49
Ramping up TGHT at 6A/min [wait interval = 10 s at increments of 1A]
Wednesday, July 07, 2021, 15:58
IGP1= 5.7 e-5 Torr and trending down. Will start ramp up to 450A at 18A/min [wait interval 10s at 3A increments]
Wednesday, July 07, 2021, 16:20
IGP1= 2.2e-3 Torr
Will continue ramping TGHT to 500A and watch pressure
Wednesday, July 07, 2021, 16:26
Continue ramping to 550 at 3A/10s
Wednesday, July 07, 2021, 16:29
holding at 550A, 5.1V for 8 hours
Wednesday, July 07, 2021, 23:41
TGHT = 550A, 5.7 V
begin ramp down at -2A/min to 450A and leave for 8 hours
Thursday, July 08, 2021, 08:20
IGP1= 2.7 e-06 Torr
TGHT = 450A, 4.5V
Will start ramp down at -2A/min to 0A
|