  Evaporator_1  Not logged in ELOG logo
Entry  Thursday, October 11, 2018, 18:13, John Wong, UC2, , LP-SIS, In progress, Conditioning UCx#25 UC#25_conditioning.JPGUC#25_conditioning-450A.JPG
    Reply  Tuesday, October 23, 2018, 10:24, Marla Cervantes, UC2, , LP-SIS, Problems, Conditioning UCx#25 
       Reply  Tuesday, October 23, 2018, 10:49, Marla Cervantes, UC2, , LP-SIS, Problems resolved, Conditioning UCx#25 
          Reply  Tuesday, October 23, 2018, 10:55, Marla Cervantes, UC2, , LP-SIS, Done, Conditioning UCx#25 OrangeCoat.jpgIonizerTube.jpgClosedSide.jpg
Message ID: 225     Entry time: Tuesday, October 23, 2018, 10:55     In reply to: 224
Author: Marla Cervantes 
Target Material: UC2 
Target Oven W.O#:  
Source: LP-SIS 
Status: Done 
Subject: Conditioning UCx#25 

Marla Cervantes wrote:

Marla Cervantes wrote:

John Wong wrote:

Thursday, October 11, 2018, 18:06

Target consists of 284 UCx discs, total packing length of 8.0 cm. 

Container was previously coated/sintered with TaC (see elog #417) in Evap#2 with TGHT set to 400A and TBHT 230A, but there was a problem with the readback.  Will ramp up TGHT to 400A to see if the carbonization is complete; if not, additional 50A on TGHT can be applied.

One end-cap is inserted on the right, wrt to the ionizer, and left end is open. 

Vacuum initial setting:

Good Vac = 5.0 e-5 Torr, Bad vac = 8.0 e-5 Torr.

pressure level will be monitored accordingly...

Auto-ramping setting

TGHT: 60 wait time, 0.2A/min, final 400A (or addtional of 50 A if required as mentioned above)

TGHT: 60 wait time, 0.2A/min, final 230A.

 Chamber is currently being pumped down.


 Friday, October 12, 2018, 15:35

Chamber has pumped down to 1.8e-6 Torr. 

Stepping up TGHT and TBHT to 40A.


 Friday, October 12, 2018, 17:07

TGHT/TBTH was held at 40A reaching max pressure of 1.7e-5 before slowly coming down. 

Initiated autoramping.


 Thursday, October 18, 2018, 11:10

TGHT reached to 400A/3.98V, pressure is coming down from the upper limit at around 320A which indicated the carbonization is approaching to completion (see attachment#1).  However, two more out-gassing steps are typically observed as TGHT reached around 450 A (see previous UCx conditioning process).  Currently the pressure is at 1.04 e-5 torr. 

Auto-ramping TGHT to 450A at 1A/min, continue to observe the vacuum...


 Thursday, October 18, 2018, 12:57

TGHT reached to 450A/4.6V. Pressure is coming down from 1.6 e-5 Torr. (see attachment#2).  Will remain at this heating current until pressure reached to mid 10-6 torr.


 

 Friday, October 19, 2018, 10:00

TRIUMF had a total power outage, the TBHT  and TGHT current had been ramped down already.


 

  Sunday, October 21, 2018, 1:00 pm

the pumps went out, and the communication with the IEVAP was recovered on Sunday, the vacuum was 160 mTorr,

the pumps were turned on again.


 

 Monday, October 22, 2018, 9:00

The target was transferred to the Ar glove box.


 Tuesday, October 23, 2018, 10:19

Target was inspected:

- Discs were in place

- Orange coating formed on the open end of target container

Spring was removed, two graphite discs were introduced, end cap was placed.

Attachment 1: OrangeCoat.jpg  172 kB  | Hide | Hide all
OrangeCoat.jpg
Attachment 2: IonizerTube.jpg  142 kB  | Show | Hide all
Attachment 3: ClosedSide.jpg  150 kB  | Show | Hide all
ELOG V2.9.2-2455