  Evaporator_1  Not logged in ELOG logo
Message ID: 214     Entry time: Wednesday, July 11, 2018, 17:44
Author: John Wong 
Target Material: UO2/C 
Target Oven W.O#:  
Source: TARGET BOAT 
Status: Done 
Subject: Processing UC2Flk_21 

Wednesday, July 11, 2018, 17:41

Cast prepared by Marla (see note in Hotlab)

Target boat contained about 50g UO2 powder. 

TGHT will be ramped up to 520A.

Vacuum limit stop at 3.0 e-4 Torr, backing off at 6.0e-4 Torr. 

Chamber is currently being pumped down


 Thursday, July 12, 2018, 10:45

Pressure at 8.9e-7 Torr. 

Initiate auto ramping TGHT at 0.1A/min to reach 580A (will monitor vacuum to ensure complete carbonization)


 Wednesday, July 18, 2018, 10:23

TGTH at 369A/3.7V, carbonization in progress. 

Pressure limited was set to 5.0e-5 Torr; change limit to 6e-4 Torr (as indicated above)

Increase ramping rate to 0.2A/min.


 Thursday, July 19, 2018, 12:12

Completion of the U-carbonization has been reached. 

Cooling down TGHT at 2A/min

Chamber will be vented in Ar and materials will be transferred to Ar glovebox


 