Tue Apr 12 10:29:38 2011: Target wrapped with 3 Ta-heat shields. Evaporator is currently being pumped down.
Tue Apr 12 15:03:55 2011: Evaporator has been pumped down for over 4 hrs. Set TGHT @ 20A/ 0.066V, Vac @ 2.46e-6 Torr. (See Attachment#1 pumping down process).
Tue Apr 12 15:05:11 2011: TGHT @ 40A/0.142V, VAc @ 2.46e-6 Torr.
Tue Apr 12 15:14:16 2011 Auto heating process begins (See attachment #2 for the parameter setup). TGHT will reach to 820A max at around 21:45 and the current will stay there for at least 4 hours. Instructions have given to ISAC Ops to being the auto-cooling down process tomorrow at 03:00
Wed Apr 13 10:00:13 2011: TGHT reached to 820A max and stayed for about 5 hrs before the cooling process begun (see Attachment#2: Cooling down process).
Wed Apr 13 10:04:19 2011: p/s is now off and evaporator is now vented.
|