Message ID: 118     Entry time: Wednesday, August 19, 2015, 11:44
Author: Laura Lambert 
Target Material: UO2/C 
Target Oven W.O#: 40282-1 
Source: TARGET BOAT 
Status: Done 
Subject: Processing UC2Flk_08 

 Wednesday, August 19, 2015, 11:02

UO2/C green was prepared Aug 11, 2015. The slurry was cast on a piece of glass coated with WD40 on Aug 12, 2015.

The cast peeled off the glass nicely Aug 14, 2014 and finished drying over the weekend. [see attached picture]

Some materials were stuck on the WC jar wall and balls, consistent with every time.

Initial UO2 powder used = 50.34g (Inventory R-00835A, UO2 + bottle = 343.60g before use)

Graphite powder used = 10.14g

Green cast dried UO2/C + organic mass = 61.42g

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat is wrapped with 3-layers of heat shield and installed in Evap1.

Chamber has been pumped down overnight, currently at IG1 = 2.5e-6 Torr.

Manually stepping up to 35A.

Target boat will be ramped up to 520A at the rate of 0.1A/min.

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr.


 Wednesday, August 19, 2015, 14:05

Waited ~2.5hrs, vacuum stable.

IG1 = 1.2e-5 Torr.

Initiating auto-ramp.


 Monday, August 31, 2015, 09:38

EVAP 1 tripped off saturday 29th, due to a power outage with TGHT = ~450A at time of trip-off.

EVAP1 lost vacuum for ~4.5hrs [see archived photo]

Visual check performed of EVAP1 - OK.

IGP1 = 6.4e-7 Torr.

Re-initiating carbonization process.


 Monday, August 31, 2015, 10:05

Tapped up manually to 30A.

Vacuum stable.

Initiating auto-ramp at 2.0A/min to a final setpoint of 200A.


 Monday, August 31, 2015, 11:33

Increased max setpoint to 250A at 2.0A/min.

According to the archive, step 1 of the carbonization process was complete and vacuum dropped at ~TGHT = 250A

Vacuum still stable IGP1 = 2.7e-6 Torr.

Once 250A achieved, changed auto ramp to 0.2A/min with a final setpoint of 300A over lunch.

Will tap up manually after lunch.


 Monday, August 31, 2015, 13:07

IGP1 = 1.66e-6 Torr.

TGHT = 262A, 2.3V

Turning off auto-ramp, taking over manually...


 Monday, August 31, 2015, 16:15

Tapped up manually to TGHT = 355A, 3.5V

IGP1 = 5.8e-6 Torr.

Re-initiating auto-ramp at 0.1A/min with a final setpoint of 520A


 Wednesday, September 02, 2015, 09:04

IG1 = 7.5e-6 Torr

TGHT = 520A, 5.53V

TGHT remained at max setpoints ~12.5hours.

Carbonization process is complete.

Initiating auto-cool at 2.0A/min.


 Thursday, September 03, 2015, 11:55

UCx vented in Ar, removed from evap1 and currently in glove box this morning.

Will measure quantity obtained this afternoon.


 Thursday, September 03, 2015, 13:27

Attached are a few notable striptool screenshots from the entire carbonization process.

UCxflk_08 = 46.926g


 

Attachment 1: IMG_20150813_151855494.jpg  2.104 MB  | Show | Hide all
Attachment 2: vacuum_trip_off.JPG  24 kB  Uploaded Monday, August 31, 2015, 10:41  | Show | Hide all
Attachment 3: carbonization_pre-power_outage_trip-off.JPG  59 kB  Uploaded Monday, August 31, 2015, 14:11  | Show | Hide all
Attachment 4: entire_carbonization.JPG  74 kB  Uploaded Thursday, September 03, 2015, 14:28  | Show | Hide all
Attachment 5: power_outage.JPG  42 kB  Uploaded Thursday, September 03, 2015, 14:29  | Show | Hide all
Attachment 6: round2_carbonization.JPG  70 kB  Uploaded Thursday, September 03, 2015, 14:29  | Hide | Hide all
round2_carbonization.JPG
Attachment 7: max_setpoints_-_round2_carbonization.JPG  92 kB  Uploaded Thursday, September 03, 2015, 14:29  | Show | Hide all
Attachment 8: final.jpg  2.924 MB  Uploaded Thursday, September 03, 2015, 16:16  | Show | Hide all