The OLIS 1 week shutdown has been completed (WP 2015-04-13-1).
General-
Y-Box insulators were inspected and look good. Beamline optics were inspected.
MWS-
The La disk was removed. Source housing was cleaned and re-asssembled with a beaker installed.
MCIS-
The cart was installed in the HV cage. Kr gas pack was installed on the cart and the transfer tube was opened up to MCIS vacuum.
SIS-
Source PE and EE assembly was removed and opened up for inspection. A new source was assembled (1/4 Ta tube and 0.040 Ta Oven & Ionizer wires) and installed. Lithium Nitrate Anhydrous (ALFA #13405 TR#205938) was inserted in the oven.
Additional details-
M:\OLIS\OFF LINE ION SOURCE\DOCUMENTS\Shutdown Work
OLIS MWS is currently running an producing 22Ne2+
|