MCIS-
the source is off. It is under vacuum and in the HV cage.
SIS-
the test filament assembly has been removed for inspection and the port blanked. Ray D. noticed that the Swagelok connections for the water manifold are extremely close to each other (potential short). Yesterday, when reducing the current on the ionizer the voltage varied significantly. The currently on the FC also changed.
The temporary collimator installed in the 4-1/2 CF port has been modified. the through hole opening has been increased from 3mm diameter to 6mm diameter.
|