Message ID: 487     Entry time: Wed Oct 22 07:58:32 2014
Author: Brian Minato 
Type: Other 
Category: General 
Subject: MCIS Work 

The remaining connections were done on the MCIS. 

A piece of 1/8" teflon was installed between the back of the sputtering tube/motor and the HV cage.

Ray confirmed the cart power supplies (heater and sputtering) Epics page readouts for Voltage and Current are okay.  The Heater p/s was left plugged into the cart receptacle.  The Sputtering p/s's are unplugged.

The MCIS:FC0 OUT limit was not actuating.  It was adjusted.

Keerthi tested the oven last night and was getting Se (14/10/24 it appeared to be Se, but the Prague magnet was not working.  Further investigation revealed it was not).  The oven supply is currently bypassed and ON.

 

Evigeny is working on the Alga and CPI amplifiers.  Both signal generators and the amplifiers are powered ON and connected.  Alga to the dummy load and CPI to the MCIS.