Last moments of beam development for SEBT commissioning. Attached is an FC6 plot and the present optics and 1mm slits. Decision was to not do a vertical emittance scan at this time, but proceed with 15Kr development, up next. Before we shut off, one last emittance scan coming up.
Later... Emittance scan with 2.5mm slits (default position setting used) in progress... Done. 101203_1017ILTEMIT.txt. Looks a little boxy... Both raw and cleaned-up versions attached.
Next: Emittance scan with 5mm slits... Done. 101203_1039ILTEMIT.txt. Looks a little more boxy... Both raw and cleaned-up versions attached.
Next: Repeat scan with original 1mm slits and scanner settings... Done. 101203_1104ILTEMIT.txt. It reproduced. Both raw and cleaned-up versions plus scanner panel attached.
Next: Quick look at 16O beams before shutting off... |