Message ID: 32     Entry time: Tue Jun 23 18:04:30 2009
Author: Damien Gallop 
Type: Routine 
Category: General 
Subject: MCIS HV conditioning to 20KV 

Supernanogan bias for this run is 16.32KV. After we were finished with source tuning, etc., we conditioned up to 20KV. Then beam was returned and 16O2+ tuned saved as 090623_1730.snapmcisfc6. Next step: Prepare MWS for dual operation. Source open now for source gas installation. Then Keerthi will develop a daul-mode tune, where the B1A bender only need be switched on or off to run either the MCIS or MWS source.