Message ID: 315     Entry time: Mon Jul 19 10:56:53 2010
Author: Damien Gallop 
Type:  
Category:  
Subject: 12C2+ for TIGRESS 

Beam from the Supernanogan remains on standby for TIGRESS pilot beam. There were a couple of source trips over the weekend, at least one a consequence of a power bump that took out a few other things too.

We have had a couple of pending work permits in the queue for a while. One is for germanium beam development, and one is for OLIS leak checking. The benefit of carrying out this work is assured delivery of 74Ge for the upcoming TITAN run, rescheduled to begin Wednesday. Note that if a leak is found and repaired on the Supernanogan side, there will be a minimum of three days pumping required before sufficient vacuum will be achieved to generate multi-charge ions.