Maintenance Day for OLIS started late yesterday afternoon. Source up at end of the day. See attached Stripchart and in particular how the source (blue trace is beam at FC6) came back to its nominal state within a reasonable time. Maintenance TBC after lunch.
Later... Hardware maintenance complete. Source HV and source gas tests followed by source startup around 16:30. Next up: magstab development.
Later... Magstab development done for this set. System up and ready for accelerator commissioning and development in the morning. Attached: starting mag field plus a Stripchart of the day. |