Beam was used last week for DRAGON commissioning. Successful run, completed yesterday, as reported by Colin this morning.
Milestone: First coasting beam through new SCC on Thursday, 8-Apr-2010 at ~20:00, using 16O(1+)4+ at 1.5MeV/u from MWS.
This week's agenda: ISAC-II commissioning and development. Maintenance Day either Tuesday or Wednesday.
Later... Marco has been tuning most of the day. He is done for now. I am taking the opportunity to work with the OLIS separator field stability program. It has been offline since at least last week, and no action taken. Attached are present state of things. |