| 21Ne has been available from the MWS since mid-week. Here is roughly how last week unfolded to now: Monday: MCIS -> MWS and remove MCIS cartTuesday: leakcheck MWS source gas manifold
 Wednesday: Controls fixed interlock oddity on IOS:BIAS
 Wednesday: Begin setup for TUDA-II
 Thursday: continue tuning to TUDA-II
 Thursday: prepare to commission new SEBT NIM
 Friday: commissioning of new SEBT NIM
 Friday night: begin setup of beam to TUDA-II
 Saturday: 21Ne5+ delivery to TUDA-II began at about 07:30 for the first time
 Saturday: 21Na5+ delivery to TUDA-II switch at about
 Saturday evening: power bumps knocked out OLIS and other systems - thunderstorms - go idle for the night
 Sunday afternoon: check tune with pilot beam
 Sunday night: resume RIB delivery
 I expect several energy changes over the next little while. At the Beam Delivery meeting today, we discussed the up-coming 25Mg run, which has scheduled a mere 48h of turnaround time. I made it known that there is *no* margin in that time allocation. I put in a bid for the preceding Friday, August 1st. Marco didn't think it would be available that soon. |