OLIS Logbook General
  General  Not logged in ELOG logo
Message ID: 112     Entry time: Mon Jul 27 14:39:22 2009
Author: Damien Gallop 
Type:  
Category:  
Subject: 21Ne5+ to TUDA-II 

21Ne has been available from the MWS since mid-week. Here is roughly how last week unfolded to now:

Monday: MCIS -> MWS and remove MCIS cart
Tuesday: leakcheck MWS source gas manifold
Wednesday: Controls fixed interlock oddity on IOS:BIAS
Wednesday: Begin setup for TUDA-II
Thursday: continue tuning to TUDA-II
Thursday: prepare to commission new SEBT NIM
Friday: commissioning of new SEBT NIM
Friday night: begin setup of beam to TUDA-II
Saturday: 21Ne5+ delivery to TUDA-II began at about 07:30 for the first time
Saturday: 21Na5+ delivery to TUDA-II switch at about
Saturday evening: power bumps knocked out OLIS and other systems - thunderstorms - go idle for the night
Sunday afternoon: check tune with pilot beam
Sunday night: resume RIB delivery

I expect several energy changes over the next little while.

At the Beam Delivery meeting today, we discussed the up-coming 25Mg run, which has scheduled a mere 48h of turnaround time. I made it known that there is *no* margin in that time allocation. I put in a bid for the preceding Friday, August 1st. Marco didn't think it would be available that soon.

ELOG V2.9.2-2455