| We discussed whether or not to leave the Supernanogan in the OLIS Faraday cage, and decided no, because the up-coming runs will use the MWS at 42 and 52kV respectively, higher than the MCIS HV rating. Bonus: We have more working room in the cage. The cart is out and parked. Services are connected and up. Run Plan: 
    Remove MCIS cart.Set up for leak-checking MWS gas manifold.Pump manifold through IOS volume.Repair leaks as necessary.Pump.Start MWS with 21Ne beam.  Beam to scheduled user at 08:30 Friday. TUDA-II safety commissioning is planned for Thursday. Sophia will need beam prior in order to set up into SEBT. |