Mon Jun 7 09:24:47 2010, Doug Preddy, Quench Recovery, started flow to power leads
|
|
Mon Aug 9 14:27:12 2010, Doug Preddy, Shut Down, Helium plant shut down
|
|
Thu Nov 11 15:46:40 2010, Doug Preddy, Other, switched to parallel cold return
|
At 14:45. |
Fri Nov 12 16:54:50 2010, Doug Preddy, Normal Running, Solenoid ramped up
|
|
Tue Oct 12 13:00:08 2004, Curtis Ballard, Start Up, cv142 valve
|
Curtis closes and opens slowly at about 11:00 am this morning. Wants to see
if that works better than the sudden on/off switch.
|
Tue Sep 18 18:48:11 2007, Curtis Ballard, Maintenance, cold box leak check
|
The leak check of the cold box diff pump fittings. Found a leak at the
base of the diff pump on the tee that is apparently used to fill the pump
with oil. The fitting was removed and a plug was removed that resembled a
|
|